Necessary Inspections


                          
 

                          
The following is a list of construction projects where inspections are required. If you have additional concerns or questions, please 348-2671 to speak with someone in the Engineering Department.

                          
 

                          
A. Residential (house or accessory building)

                          
____ 1. Footing (before pour)

                          
____ 2. Plumbing under slab (before slab preparation)

                          
____ 3. Slab (before pour)

                          
____ 4. Framing (before insulation/dry wall)

                          
____ 5. Rough electrical (same as # 4)

                          
____ 6. Rough plumbing (same as # 4)

                          
____ 7. Rough mechanical (same as # 4)

                          
____ 8. Electrical service (just prior to final)

                          
____ 9. Sewer (hook up to sewer lines)

                          
___ 10. Final plumbing (prior to occupation)

                          
___ 11. Final electrical (same as # 10)

                          
___ 12. Final mechanical (same as # 10)

                          
 

                          
B. Service Upgrade or Repair

                          
___ 1. Electrical (prior to hook up by utility company)

                          
 

                          
C. Commercial (non-residential construction)

                          
____ 1. Footing/foundation pads (prior to pour)

                          
____ 2. Plumbing under slab (before slab pour)

                          
____ 3. Slab (before pour)

                          
____ 4. Framing (prior to insulation/dry wall)

                          
____ 5. Rough plumbing in wall (same as # 4)

                          
____ 6. Rough electrical in wall (same as # 4)

                          
____ 7. Ceiling inspection (prior to insulation/dry wall installation-

                          
        includes rough plumbing, electrical, and mechanical)

                          
____ 8. Electrical service (prior to final)

                          
____ 9. Sewer (same as # 8)

                          
___ 10. Final plumbing (prior to occupation)

                          
___ 11. Final electrical (same as # 10)

                          
___ 12. Final mechanical (same as # 10)

                          
___ 13. Final inspection (same as # 10-performed by fire chief and code 

                          
        enforcer)

                          
 

                          
D. Swimming Pools

                          
____ 1. Grounding/bonding (prior to concrete)

                          
____ 2. Rough wiring (conduit run)

                          
____ 3. Final electrical (when complete)

                          
____ 4. Fence inspection (within one month of completion)

                          
 

                          
E. Other types of structures

                          
Inspection depending on type- will be determined case by case.